Our projects

Building 4.07 in the King Abdullah Financial District

  • Inspected 4,100 square feet of pre-installed ductwork to determine if they needed modifications.
 
  • Applying a fire-resistant coating to pre-installed air ducts to make them compliant with civil defense requirements. Duration: 45 days.

Building 4.08 in the King Abdullah Financial District

  • Inspected 3,070 square feet of pre-installed ductwork to determine if modifications were needed.
 
  • Applying a fire-resistant coating to pre-installed air ducts to make them compliant with civil defense requirements. Duration: 35 days.

Building 2.14 in the King Abdullah Financial District

  • Inspected 1,300 square feet of pre-installed ductwork to determine if they needed modifications.
 
  • Applying a fire-resistant coating to pre-installed air ducts to make them compliant with civil defense requirements. Duration: 40 days

Building 4.02 in the King Abdullah Financial District

  • Inspect 2,000 square feet of pre-installed ductwork to determine if they need modifications
 
  • Apply a fire-resistant coating to pre-installed air ducts to make them compliant with civil defense requirements. Duration: 30 days.

Building 4.01, 4.03,

  • Inspection of 13,000 square feet of pre-installed ductwork to determine if modifications are needed. Duration: 60 days.